Southmere Village Park Detention Pond Cleanout

 


Description

Southmere Village Park - Detention Pond Cleanout


Details

Works consisted of excavation of accumulated sediment from the Southmere Village detention ponds including bypass pumping of storm water as required to complete the work. Excavated sediment was contained in areas constructed onsite to allow to partially dry before hauling offsite. Supply and install sluice gates, re and re pathways around two ponds and restoration of all disturbed areas. Public relations with local residents in and around the park was a key to completing this project.

Value

$403,737

Year

2012

Owner

City of Surrey

Refer to

Doug Mossey (604-591-4787)

Arch./Eng.

AECOM Canada Ltd.

Refer to

Scott Neuman, P. Eng. (604-444-6400)