Hyde Creek - In-Stream Works Improvement Contract


Details

The project involved the reconstruction of retaining walls down the steep embankment along Whatkins Creek. This erosion-prone section was with a new lock block wall retaining system and riprap lining, and also included instream work to enhance environment recovery.

Value

$295,000

Year

2007

Owner

City of Coquitlam

Refer to

Chad Braley, AScT (604-927-3513)

Arch./Eng.

Earth Tech (Canada) Inc.

Refer to

Scott Neuman, P.Eng. (604-298-6181)